Project Schedule
Phase 1 Construction
Central Plant Construction Completed
|
October 2009 |
| Construction of Buildings 201 and 202 Completed |
October 2010 |
| Construction of Parking Structure A Completed |
December 2010 |
| Construction of Buildings 203 and 204 |
January 2011 - Spring 2012 |
Summary of Construction Schedule
Two Phases: Total Construction Duration 5+ years (Fall 2008 - Winter 2013)
Phase 1
October 2008 – Spring 2012 |
Phase 2
Fall 2012 – Spring 2014 |
Phase 1
Central Plant and Utilities: Oct 2008 - Oct 2009 (12 months / completed)
- Construct New Central Plant and Utility Infrastructure
Phase 1A Building Construction: March 2009 - February 2011
- Demolish Buildings 8 and 10 (completed)
- Demolish Building 9 and 14 (completed)
- Construct New Office Building 201 - 5500 Overland Avenue (completed)
- Construct New Office Building 202 - 5560 Overland Avenue (completed)
- Construct Parking Structure A (completed)
- Hazard Way Renovations (in progress)
Phase 1B Construction: Winter 2011 - Spring 2012
- Demolish: Buildings 1, 2 and 15 (completed)
- Demolish Buildings: 3, 4, 16 and 17 (completed)
- Construct: Two New Office Buildings (203 and 204) and Conference Center (In progress)
- Fleet Garage Improvements
Phase 2
Phase 2 Building Construction: Fall 2012 – Spring 2014
*Subject to Board of Supervisors Funding Approval
- Construct: Two New Office Buildings (205 and 206) and Parking Structure B