Project Schedule
Phase 1 Construction
Central Plant Construction Completed
|
October 2009 |
| Construction of Buildings 201 and 202 |
March 2009 through Fall 2010 |
| Construction of Parking Structure A |
January 2010 through Winter 2011 |
Summary of Construction Schedule
Two Phases: Total Construction Duration 5+ years (Fall 2008 - Winter 2013)
Phase 1
October 2008 – Spring 2012 |
Phase 2
Fall 2012 – Spring 2014 |
Phase 1
Central Plant and Utilities: Oct 2008 - Oct 2009 (12 months / completed)
- Construct New Central Plant (Building 200) and Utility Infrastructure
Phase 1A Building Construction: March 2009 - February 2011
- Demolish Buildings 8 and 10
- Demolish Building 9 and 14
- Construct Two New Office Buildings (201 and 202)
- Construct Parking Structure A
- Hazard Way Renovations
Phase 1B Construction: Winter 2011 - Spring 2012
*Subject to Board of Supervisors Funding Approval
- Demolish: Buildings 1, 2, 3, 4, 5, 6, 15, 16 & 17
- Construct: Two New Office Buildings (203 and 204) and Conference Center
- Fleet Improvements
Phase 2
Phase 1A Building Construction: Fall 2012 – Spring 2014
*Subject to Board of Supervisors Funding Approval
- Construct: Two New Office Buildings (205 and 206) and Parking Structure B