Project Schedule
Phase 1: Near Term Outlook
Central Plant Construction Start
|
October 1, 2008 |
| Building 8 & 10 Occupants Relocation |
February 2009 |
| Demolition of Buildings 8 & 10 |
March 2009 |
| Construction of Buildings 201 and 202 |
March 2009 through Spring 2010 |
Summary of Construction Schedule
Two Phases: Total Construction Duration 5+ years (Fall 2008 - Winter 2013)
Phase 1
October 2008 – December 2010 |
Phase 2
Spring 2012 – Winter 2013 |
Phase 1
Central Plant and Utilities: Oct 2008 - Oct 2009 (12 months/ in progress)
- Construct New Central Plant (Building 200) and Utility Infrastructure
Phase 1A Building Construction: March 2009 - Sept. 2010 (19 months)
*Subject to Board Funding in January 2009
- Demolish Building 8, 9, 10, & 14
- Construct Two New Office Buildings (201 and 202) and Parking Structure A
17 months (Fall 2010 – Spring 2012)
*Subject to Full Board Funding
- Demolish: Buildings 1, 2, 3, 4, 5, 6, 15, 16 & 17
- Construct: Two New Office Buildings (203 and 204) and Conference Center
- Fleet Improvements
Phase 2
*Subject to Full Board Funding
21 months (Spring 2012 – Winter 2013)
- Construct: Two New Office Buildings and Parking Structure B