Project Schedule

Phase 1 Construction

Central Plant Construction Completed
October 2009
Construction of Buildings 201 and 202 Completed October 2010
Construction of Parking Structure A Completed December 2010
Construction of Buildings 203 and 204 January 2011 - Spring 2012

 

Summary of Construction Schedule

Two Phases: Total Construction Duration 5+ years (Fall 2008 - Winter 2013)

Phase 1
October 2008 – Spring 2012
Phase 2
Fall 2012 – Spring 2014

Phase 1

Central Plant and Utilities: Oct 2008 - Oct 2009 (12 months / completed)

  • Construct New Central Plant and Utility Infrastructure

Phase 1A Building Construction: March 2009 - February 2011

  • Demolish Buildings 8 and 10 (completed)
  • Demolish Building 9 and 14 (completed)
  • Construct New Office Building 201 - 5500 Overland Avenue (completed)
  • Construct New Office Building 202 - 5560 Overland Avenue (completed)
  • Construct Parking Structure A (completed)
  • Hazard Way Renovations (in progress)

Phase 1B Construction: Winter 2011 - Spring 2012

  • Demolish: Buildings 1, 2 and 15 (completed)
  • Demolish Buildings: 3, 4, 16 and 17 (completed)
  • Construct: Two New Office Buildings (203 and 204) and Conference Center (In progress)
  • Fleet Garage Improvements

Phase 2

Phase 2 Building Construction: Fall 2012 – Spring 2014
*Subject to Board of Supervisors Funding Approval

  • Construct: Two New Office Buildings (205 and 206) and Parking Structure B