Monthly Report of Progress for May 2010
Office Buildings 201 and 202
- Enclosure of both buildings is completed.
- Interior improvements are well underway.
- Heating, ventilation and air conditioning systems are being installed.
Parking Structure A
- The elevator tower is in construction.
- Construction of foundations continues.
Off-site Improvements
- Improvements to Overland Avenue are underway. These will include traffic improvements, a new signal at the intersection of Overland Avenue and Farnham Street, and undergrounding of SDG&E electric lines.
- Improvements at Farnham Street and Hazard Way began are complete.
Central Plant Construction
- Construction was completed in October 2009
- Chilled water and power distribution have commenced
San Diego Medical Examiner and Forensic Center
- Construction was completed in December 2009
- The Center is now operational
Parking Management
- The COC Project provides Managed Parking (Valet Assisted Parking) for employees and visitors
- An off-site parking lot is available to employees and visitors with regular shuttle service