Summary of Construction Schedule

Two Phases: Total Construction Duration 5+ years (Fall 2008 - Winter 2013)

Phase 1
October 2008 – Spring 2012
Phase 2
Fall 2012 – Spring 2014

Phase 1

Central Plant and Utilities: Oct 2008 - Oct 2009 (12 months / completed)

  • Construct New Central Plant (Building 200) and Utility Infrastructure

Phase 1A Building Construction: March 2009 - February 2011

  • Demolish Buildings 8 and 10
  • Demolish Building 9 and 14
  • Construct Two New Office Buildings (201 and 202)
  • Construct Parking Structure A
  • Hazard Way Renovations

Phase 1B Construction: Winter 2011 - Spring 2012
*Subject to Board of Supervisors Funding Approval

  • Demolish: Buildings 1, 2, 3, 4, 5, 6, 15, 16 & 17
  • Construct: Two New Office Buildings (203 and 204) and Conference Center
  • Fleet Improvements

Phase 2

Phase 1A Building Construction: Fall 2012 – Spring 2014
*Subject to Board Supervisors Funding Approval

  • Construct: Two New Office Buildings (205 and 206) and Parking Structure B