Summary Schedule

Two Phases: Total Construction Duration 5+ years (Fall 2008 - Winter 2013)

Phase 1
October 2008 – December 2010
Phase 2
Spring 2012 – Winter 2013

Phase 1

Central Plant and Utilities: Oct 2008 - Oct 2009 (12 months/ in progress)

  • Construct New Central Plant (Building 200) and Utility Infrastructure

Phase 1A Building Construction: March 2009 - Sept. 2010 (19 months)
*Subject to Board Funding in January 2009

  • Demolish Building 8, 9, 10, & 14
  • Construct Two New Office Buildings (201 and 202) and Parking Structure A

17 months (Fall 2010 – Spring 2012)
*Subject to Full Board Funding

  • Demolish: Buildings 1, 2, 3, 4, 5, 6, 15, 16 & 17
  • Construct: Two New Office Buildings (203 and 204) and Conference Center
  • Fleet Improvements

Phase 2
*Subject to Full Board Funding

21 months (Spring 2012 – Winter 2013)

  • Construct: Two New Office Buildings and Parking Structure B